Civil works:

  • Our experienced Civil team built a bund wall and plinths for the above-ground tank.
  • Paving was laid after the Oil separation tank was installed.

Mechanical:

  • Saddles were manufactured to support the above-ground tank.
  • A pump island ballard was manufactured to ensure the safety of the pumping equipment from the vehicles.
  • All pipework, fittings, and connections to and from the above-ground diesel tank were manufactured, installed, and pressure tested.
  • Cat ladder and walkway were manufactured for easy access on top of the tank.

Installation:

  • An oil separation tank was installed.
  • 80 000lt Above ground diesel tank.